Need Help?

What are your hours?
Our office hours are 8 a.m. to 5 p.m. Monday through Friday.
How do I report an outage?
Please call 888-827-3322, text "OUT" to 85700 or use our mobile app to report an outage.
How do I pay my bill?
We offer many ways to pay your bill. You can pay using our First Electric mobile app, our website, our office or by calling 844-729-3322.
How do I get new service?
You can request new service by completing an application on our app or you can call 800-489-7405.

Thanks for your message. We’ll follow up soon.

There was a problem submitting your request. Please try again.

Preliminary Interconnection Site Review Request

Customer Information

Owner Information

Generation Facility Information

Interconnection Information

Signature

I hereby certify that, to the best of my knowledge, all the information provided in this Preliminary Interconnection Site Review is true and correct.

 

TERMS AND CONDITIONS

Section 1. Requirements for Request

For the purpose of requesting that the Cooperative conduct a preliminary interconnection site review for
a proposed Net-Metering Facility pursuant to the requirement of Rule 2.06.B.4, or as otherwise
requested by the customer, the customer shall notify the Cooperative by submitting a completed
Preliminary Interconnection Site Review Request. The customer shall submit a separate Preliminary
Interconnection Site Review Request for each point of interconnection if information about multiple
points of interconnection is requested. Part 1, Standard Information, Sections 1 through 4 of the
Preliminary Interconnection Site Review Request must be completed for the notification to be valid. If
mailed, the date of notification shall be the third day following the mailing of the Preliminary
Interconnection Site Review Request. The Cooperative shall provide a copy of the Preliminary
Interconnection Site Review Request to the customer upon request.

Section 2. Utility Review

Following submission of the Preliminary Interconnection Site Review Request by the customer the
Cooperative shall review the plans of the facility interconnection and provide the results of its review to
the customer, in writing, within 30 calendar days. If the customer requests that multiple interconnection
site reviews be conducted the Cooperative shall make reasonable efforts to provide the customer with
the results of the review within 30 calendar days. If the Cooperative cannot meet the deadline it will
provide the customer with an estimated date by which it will complete the review. Any items that
would prevent Parallel Operation due to violation of safety standards and/or power generation limits
shall be explained along with a description of the modifications necessary to remedy the violations.

The preliminary interconnection site review is non-binding and need only include existing data and
does not require the Cooperative to conduct a study or other analysis of the proposed interconnection
site in the event that data is not readily available. The Cooperative shall notify the customer if
additional site screening may be required prior to interconnection of the facility. The customer shall be
responsible for the actual costs for conducting the preliminary interconnection site review and any
subsequent costs associated with site screening that may be required.

Section 3. Application to Exceed 1,000 kW Net-Metering Facility Size Limit

This Preliminary Interconnection Site Review Request and the results of the Cooperative’s review of the facility interconnection shall be filed with the Commission with the customer’s application to exceed the 1,000 kW facility size limit pursuant to Net Metering Rule 2.06.B.4.

Section 4. Standard Interconnection Agreement

The preliminary interconnection site review does not relieve the customer of the requirement to execute a Standard Interconnection Agreement prior to interconnection of the facility.